DECISIONS

IN THE

SUPREME COURT OF THE UNITED STATES,

DECEMBER TERM, 1864.

DERMOTT V. Jones.

1. Performance of a contract to build a house for another on the soil of such person, and that the work shall be executed, finished, and ready for use and occupation, and be delivered over so finished and ready to the owner of the soil, at a day named, is not excused by the fact that there was a latent defect in the soil, in consequence of which the walls sank and cracked, and the house, having become uninhabitable and dangerous, had to be partially taken down and rebuilt on artificial foundations. 2. While a special contract remains executory the plaintiff must sue upon it. When it has been fully executed according to its terms, and nothing remains to be done but the payment of the price, he may sue either on it, or in indebitatus assumpsit, relying, in this last case, upon the common counts; and in either case the contract will determine the rights of the parties.

3. When he has been guilty of fraud, or has wilfully abandoned the work, leaving it unfinished, he cannot recover in any form of action. Where he has in good faith fulfilled, but not in the manner nor within the time prescribed by the contract, and the other party has sanctioned or accepted the work, he may recover upon the common counts in indebitatus assumpsit.

4. He must produce the contract upon the trial, and it will be applied as far as it can be traced; but if, by fault of the defendant, the cost of the work or material has been increased, in so far the jury will be warranted in departing from the contract prices. In such case the defendant is entitled to recoup for the damages he may have sustained by the plaintiff's deviations from the contract, not induced by himself, both as to the manner and time of the performance.

JONES, a mason and house-builder, contracted with Miss Dermott to build a house for her, the soil on which the house was to be built being her own. The house was to be built

[blocks in formation]

Statement of the case.

according to very detailed plans and specifications, which the "architect" of Miss Dermott had prepared, and which were made part of the contract. In the contract, Jones coveranted that he would procure and supply all matters requisite for the execution of the work "in all its parts and details, and for the complete finish and fitting for use and occupation of all the houses and buildings, and the several apartments of the house and buildings, to be erected pursuant to the plan of the work described and specified in the said schedule; and that the work, and the several parts and parcels thereof, shall be executed, finished, and ready for use and occupation, and be delivered over, so finished and ready," at a day fixed. Jones built the house according to the specifications, except in so far as Miss Dermott had compelled him,-according to his account of things, to deviate from them. Owing, however, to a latent defect in the soil, the foundation sank, the building became badly cracked, uninhabitable, and so dangerous to passersby, that Miss Dermott was compelled to take it down, to renew the foundation with artificial "floats," and to rebuild that part of the structure which had given way. This she did at a large expense. As finished on the artificial foundations the building was perfect.

Jones having sued Miss Dermott, in the Federal Court for the District of Columbia, for the price of building, her counsel asked the court to charge that she was entitled to "recoup" the amount which it was necessary for her to expend in order to render the cracked part of the house fit for use and occupation according to the plan and specifications; an instruction which the court refused to give. The court considered, apparently, that even under the covenant made by Jones, and above recited, he was not responsible for injury resulting from inherent defects in the ground, the same having been Miss Dermott's own; and judgment went accordingly. Error was taken here. Some other questions. were presented in the course of the trial below, and referred to here; as, for example, How far, when a special contract has been made, a plaintiff must sue upon it? how far he may recover in a case where, as was said to have been the fact

Argument for the builder.

here, the plaintiff had abandoned his work, leaving it unfinished? how far "acceptance," when such acceptance consisted only in a party's treating as her own a house built on her ground,-waives non-fulfilment, there being no bad faith in the matter? and some questions of a kindred kind. The most important question in the case, however, was the refusal of the court to charge, as requested, in regard to the "recoupment:" and the correctness of that refusal rested upon the effect of Jones's covenant to deliver, fit for use and occupation, in connection with the latent defect of soil upon which the foundation was built.

Messrs. Carlisle and Davidge for the builder: In all cases of locatio operis faciendi, where a workman undertakes to incorporate his work and materials with the property of another, and loss is sustained in consequence of some inherent defect in the property, the loss falls upon the employer. The maxim of res perit domino applies. Pothier, according to Story, thus declares the law of France. It is also Scotch law. By it, if the workman is employed in working the materials, or adding his labor to the property of the employer, the risk belongs to the owner of the thing with which the labor is incorporated.† The employer, by the code of France, is the guarantor of the thing upon which the work and materials of the workman are to be expended: the code of Louisiana adopts the same rule: and the common law is the same. "If the loss in bad execution," says Kent,‡ "is not properly attributable to the fault or unskilfulness of the undertaker, or those employed by him, but arises from the inherent defect of the thing itself; in such a case the loss is to be borne by the employer, unless there is some agreement by which the risk is taken by the undertaker."

Undoubtedly the plaintiff might have assumed the extraordinary responsibility alleged; but, unless it be clearly shown that he did so, the presumption is that he contracted

* Bailments, 426.

† 1 Bell, 156, 5th ed.

2 Commentaries, ¿ 40.

Argument for the owner of the soil.

for no more than the sort and ȧegree of skill and diligence belonging to his trade. His covenant is not the stipulation of an insurer of anything, but is a stipulation to give his own skill, fidelity, and diligence in the prosecution of work undertaken in pursuance of prescribed specifications and plans. Miss Dermott purchased, by the contract, the skill and diligence of Jones, in supplying the work and materials stipulated, and also his judgment, so far as involved in the work and materials. But she never bought his judgment, as regarded the plans and specifications. He was never consulted about them. On the contrary, they were prepared by her architect, and put in his hands to work by. If he deviated from them, he was guilty of a breach of contract, for which he was responsible. His business was to work by, not to override them.

It is thus apparent that the present case is not one where an architect, employed to furnish plans and specifications, is guilty of neglect, and of not exercising that degree of skill and judgment which the employer prays; but is a case where a mechanic is employed to supply work and materials according to plans and specifications which he is bound to follow. The rule of law is that a party is responsible for the ordinary degree of skill belonging to his trade or profession. But Jones was not an engineer or architect, but, as the case states, "a máson and house-builder." Nor di.l Miss Dermott treat with him in any other character than that of a mechanic, competent, not to plan, but to carry out her plans. She employed an architect, by whom the plans and specifications were prepared. Her remedy, then, for any defects in the plans and specifications, was by suit against the architect, not by recoupment against Jones. The architect should have ascertained, if necessary, by boring or otherwise, whether they were practicable.

Messrs. Poe and Brent contra: The counsel of the other side do not cite one adjudged case in support of their view. The speculations of Pothier, the dicta of Story, or even the ab